This Week Jan 30- Feb 3
An electrical 50A plug wire was installed to plug, though not yet connected to the panel. We used 6 ga. wire for the installation.
90 % of the insulation installed.
Holes drilled in studs for hot and cold water lines.
Some cleaning took place in room 14.
We placed the seeds placed in the 1020s on 1/22 in room 13. Students have been watering them daily.
We also repaired the stairs to the Tiny Home after we discovered that the risers were not correctly installed to the platform causing a failure. No one was hurt during the failure.
Then we had some explorers taking the Tiny Home out of level by placing the turn handle back on the lever and lifting the Tiny Home.